Gas transmission pipeline · Midrikah remote header B to Hawiyah Gas Plant
Madrakah–Al Hawiyah Gas Pipeline
Madrakah–Al Hawiyah Gas Pipeline is an operating gas transmission pipeline in Saudi Arabia. The tracker lists 1 tracked segment, 450 km long and 2.96 bcm/y of capacity, starting up in 2024. It runs from Midrikah remote header B to Hawiyah Gas Plant. It is owned by Saudi Aramco.
Length
450 km
Capacity
2.96 bcm/y
2.2 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 914 mm (36 in)
Route
Madrakah–Al Hawiyah Gas Pipeline runs from Midrikah remote header B to Hawiyah Gas Plant. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Midrikah remote header B
- To
- Hawiyah Gas Plant
- Start country
- Saudi Arabia
- End country
- Saudi Arabia
- Countries crossed
- Saudi Arabia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 134 km
- GEM pipeline ID
- P3961
- Start year
- 2024
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Midrikah remote header B → Hawiyah Gas Plant | 450 | 2.96 | 914 mm | 2024 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Saudi Aramco100%
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Madrakah–Al Hawiyah Gas Pipeline run?
- Madrakah–Al Hawiyah Gas Pipeline runs from Midrikah remote header B to Hawiyah Gas Plant, crossing Saudi Arabia.
- How long is Madrakah–Al Hawiyah Gas Pipeline?
- Madrakah–Al Hawiyah Gas Pipeline is 450 km long.
- How much gas can Madrakah–Al Hawiyah Gas Pipeline carry?
- Madrakah–Al Hawiyah Gas Pipeline has a design capacity of 2.96 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Madrakah–Al Hawiyah Gas Pipeline operating?
- Madrakah–Al Hawiyah Gas Pipeline is operating, having started in 2024.
- Who owns Madrakah–Al Hawiyah Gas Pipeline?
- Madrakah–Al Hawiyah Gas Pipeline is owned by Saudi Aramco, as recorded in the current tracker release.