Gas transmission pipeline · Gornji Kneginec to Varaždin

Kneginec–Varaždin II Gas Pipeline

Kneginec–Varaždin II Gas Pipeline is an operating gas transmission pipeline in Croatia. The tracker lists 1 tracked segment, 8 km long and 0.54 bcm/y of capacity, starting up in 2020. It runs from Gornji Kneginec to Varaždin. It is owned by Plinacro Ltd.

Length

8 km

Capacity

0.54 bcm/y

0.4 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 200 mm (7.9 in)

Route

Kneginec–Varaždin II Gas Pipeline runs from Gornji Kneginec to Varaždin. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Gornji Kneginec
To
Varaždin
Start country
Croatia
End country
Croatia
Countries crossed
Croatia
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
6.8 km
GEM pipeline ID
P3417
Start year
2020
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingGornji Kneginec → Varaždin80.54200 mm2020GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Kneginec–Varaždin II Gas Pipeline run?
Kneginec–Varaždin II Gas Pipeline runs from Gornji Kneginec to Varaždin, crossing Croatia.
How long is Kneginec–Varaždin II Gas Pipeline?
Kneginec–Varaždin II Gas Pipeline is 8 km long.
How much gas can Kneginec–Varaždin II Gas Pipeline carry?
Kneginec–Varaždin II Gas Pipeline has a design capacity of 0.54 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Kneginec–Varaždin II Gas Pipeline operating?
Kneginec–Varaždin II Gas Pipeline is operating, having started in 2020.
Who owns Kneginec–Varaždin II Gas Pipeline?
Kneginec–Varaždin II Gas Pipeline is owned by Plinacro Ltd, as recorded in the current tracker release.