Gas transmission pipeline · Louisiana to Louisiana
Creole Trail Pipeline
Creole Trail Pipeline is a cancelled gas transmission pipeline in United States. The tracker lists 1 tracked segment, 168 km long and 15.33 bcm/y of capacity. It runs from Louisiana to Louisiana. It is owned by Cheniere Energy.
Length
168 km
Capacity
15.3 bcm/y
11.3 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 1067 mm (42 in)
Route
Creole Trail Pipeline runs from Louisiana to Louisiana. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Louisiana
- To
- Louisiana
- Start country
- United States
- End country
- United States
- Countries crossed
- United States
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 163 km
- GEM pipeline ID
- P2522
- Start year
- Not reported
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Reversal Project | Cancelled | Louisiana → Louisiana | 168 | 15.3 | 1067 mm | — | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Beacon Port LNG Terminal | United States | Import | Cancelled | 0.1 km | route proximity |
| Sabine Pass LNG Terminal | United States | Export | Operating | 1.8 km | route proximity |
| Golden Pass LNG Terminal | United States | Export | Operating | 5.9 km | route proximity |
| Port Arthur LNG Terminal | United States | Export | Under construction | 11.2 km | route proximity |
| Lake Charles LNG Terminal | United States | Import | Mothballed | 15.5 km | route proximity |
| Alturas LNG Terminal | United States | Export | Cancelled | 15.8 km | route proximity |
| Magnolia LNG Terminal | United States | Export | Proposed | 16.2 km | route proximity |
| Woodside Louisiana LNG Terminal | United States | Export | Under construction | 16.5 km | route proximity |
| Cameron LNG Terminal | United States | Export | Operating | 22.3 km | route proximity |
| Creole Trail LNG Terminal | United States | Import | Cancelled | — | name match |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Cheniere Energy100%
Parent companies
- Cheniere Energy100%