Gas transmission pipeline · Vega Pléyade platform to Rio Cullen and Cañadon Alfa gas processing plants

Vega Pléyade Gas Pipeline

Vega Pléyade Gas Pipeline is an operating gas transmission pipeline in Argentina. The tracker lists 1 tracked segment, 77 km long and 3.65 bcm/y of capacity, starting up in 2016. It runs from Vega Pléyade platform to Rio Cullen and Cañadon Alfa gas processing plants. It is owned by TotalEnergies, Wintershall Energía and Pan American Energy.

Length

77 km

Capacity

3.65 bcm/y

2.7 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 610 mm (24 in)

Route

Vega Pléyade Gas Pipeline runs from Vega Pléyade platform to Rio Cullen and Cañadon Alfa gas processing plants. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Vega Pléyade platform
To
Rio Cullen and Cañadon Alfa gas processing plants
Start country
Argentina
End country
Argentina
Countries crossed
Argentina
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
109 km
GEM pipeline ID
P2082
Start year
2016
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingVega Pléyade platform → Rio Cullen and Cañadon Alfa gas processing plants773.65610 mm2016GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Vega Pléyade Gas Pipeline run?
Vega Pléyade Gas Pipeline runs from Vega Pléyade platform to Rio Cullen and Cañadon Alfa gas processing plants, crossing Argentina.
How long is Vega Pléyade Gas Pipeline?
Vega Pléyade Gas Pipeline is 77 km long.
How much gas can Vega Pléyade Gas Pipeline carry?
Vega Pléyade Gas Pipeline has a design capacity of 3.65 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Vega Pléyade Gas Pipeline operating?
Vega Pléyade Gas Pipeline is operating, having started in 2016.
Who owns Vega Pléyade Gas Pipeline?
Vega Pléyade Gas Pipeline is owned by TotalEnergies, Wintershall Energía and Pan American Energy, as recorded in the current tracker release.