LNG Chain

Gas transmission pipeline · Vastogirardi to Oricola

Vastogirardi-Oricola Gas Pipeline

Vastogirardi-Oricola Gas Pipeline is an operating gas transmission pipeline in Italy. The tracker lists 1 tracked segment, 139 km long, starting up in 1993. It runs from Vastogirardi to Oricola. It is owned by Snam Rete Gas SpA.

Length

139 km

Capacity

Not reported

Segments tracked

1

Largest diameter 1219 mm (48 in)

Route

Vastogirardi-Oricola Gas Pipeline runs from Vastogirardi to Oricola. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Vastogirardi
To
Oricola
Start country
Italy
End country
Italy
Countries crossed
Italy
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
83 km
GEM pipeline ID
P2986
Start year
1993
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Oricola–Sulmona Gas PipelineOperatingVastogirardi → Oricola139Not reported1219 mm1993GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Vastogirardi-Oricola Gas Pipeline run?
Vastogirardi-Oricola Gas Pipeline runs from Vastogirardi to Oricola, crossing Italy.
How long is Vastogirardi-Oricola Gas Pipeline?
Vastogirardi-Oricola Gas Pipeline is 139 km long.
How much gas can Vastogirardi-Oricola Gas Pipeline carry?
No design capacity is reported for Vastogirardi-Oricola Gas Pipeline. That is an absent figure, not a zero.
Is Vastogirardi-Oricola Gas Pipeline operating?
Vastogirardi-Oricola Gas Pipeline is operating, having started in 1993.
Who owns Vastogirardi-Oricola Gas Pipeline?
Vastogirardi-Oricola Gas Pipeline is owned by Snam Rete Gas SpA, as recorded in the current tracker release.