Gas transmission pipeline · Baumgarten an der March to Arnoldstein
Trans-Austria Gas Pipeline
Trans-Austria Gas Pipeline is an operating gas transmission pipeline in Austria. The tracker lists 1 tracked segment, 380 km long and 13.67 bcm/y of capacity, starting up in 1974. It runs from Baumgarten an der March to Arnoldstein. It is owned by Trans Austria Gasleitung GmbH.
Length
380 km
Capacity
13.7 bcm/y
10.1 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 914 mm (36 in)
Route
Trans-Austria Gas Pipeline runs from Baumgarten an der March to Arnoldstein. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Baumgarten an der March
- To
- Arnoldstein
- Start country
- Austria
- End country
- Austria
- Countries crossed
- Austria
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 350 km
- GEM pipeline ID
- P0722
- Start year
- 1974
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Pipeline 1 | Operating | Baumgarten an der March → Arnoldstein | 380 | 13.7 | 914 mm | 1974 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
- Snam SpA87.5%
- Verbund AG7.9%
- Allianz SE4.6%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Trans-Austria Gas Pipeline run?
- Trans-Austria Gas Pipeline runs from Baumgarten an der March to Arnoldstein, crossing Austria.
- How long is Trans-Austria Gas Pipeline?
- Trans-Austria Gas Pipeline is 380 km long.
- How much gas can Trans-Austria Gas Pipeline carry?
- Trans-Austria Gas Pipeline has a design capacity of 13.7 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Trans-Austria Gas Pipeline operating?
- Trans-Austria Gas Pipeline is operating, having started in 1974.
- Who owns Trans-Austria Gas Pipeline?
- Trans-Austria Gas Pipeline is owned by Trans Austria Gasleitung GmbH, as recorded in the current tracker release.