Gas transmission pipeline · Olbernhau to Reckrod compressor station, Eiterfeld
STEGAL Gas Pipeline
STEGAL Gas Pipeline is an operating gas transmission pipeline in Germany. The tracker lists 1 tracked segment, 314 km long and 8 bcm/y of capacity, starting up in 1992. It runs from Olbernhau to Reckrod compressor station, Eiterfeld. It is owned by GASCADE Gastransport GmbH.
Length
314 km
Capacity
8 bcm/y
5.9 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 787 mm (31 in)
Route
STEGAL Gas Pipeline runs from Olbernhau to Reckrod compressor station, Eiterfeld. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Olbernhau
- To
- Reckrod compressor station, Eiterfeld
- Start country
- Germany
- End country
- Germany
- Countries crossed
- Germany
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 274 km
- GEM pipeline ID
- P0721
- Start year
- 1992
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Olbernhau → Reckrod compressor station, Eiterfeld | 314 | 8 | 787 mm | 1992 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does STEGAL Gas Pipeline run?
- STEGAL Gas Pipeline runs from Olbernhau to Reckrod compressor station, Eiterfeld, crossing Germany.
- How long is STEGAL Gas Pipeline?
- STEGAL Gas Pipeline is 314 km long.
- How much gas can STEGAL Gas Pipeline carry?
- STEGAL Gas Pipeline has a design capacity of 8 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is STEGAL Gas Pipeline operating?
- STEGAL Gas Pipeline is operating, having started in 1992.
- Who owns STEGAL Gas Pipeline?
- STEGAL Gas Pipeline is owned by GASCADE Gastransport GmbH, as recorded in the current tracker release.