Gas transmission pipeline · Heidelberg to Heilbronn
South German Gas Pipeline
South German Gas Pipeline is an under construction gas transmission pipeline in Germany. The tracker lists 1 tracked segment, 60 km long, starting up in 2027. It runs from Heidelberg to Heilbronn. It is owned by Terranets BW.
Length
60 km
Capacity
Not reported
Segments tracked
1
Largest diameter 1200 mm (47 in)
Route
South German Gas Pipeline runs from Heidelberg to Heilbronn. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Heidelberg
- To
- Heilbronn
- Start country
- Germany
- End country
- Germany
- Countries crossed
- Germany
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 62 km
- GEM pipeline ID
- P7516
- Start year
- 2027
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Heidelberg-Heilbronn | Under construction | Heidelberg → Heilbronn | 60 | Not reported | 1200 mm | 2027 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Terranets BW100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does South German Gas Pipeline run?
- South German Gas Pipeline runs from Heidelberg to Heilbronn, crossing Germany.
- How long is South German Gas Pipeline?
- South German Gas Pipeline is 60 km long.
- How much gas can South German Gas Pipeline carry?
- No design capacity is reported for South German Gas Pipeline. That is an absent figure, not a zero.
- Is South German Gas Pipeline operating?
- South German Gas Pipeline is under construction, with a reported start year of 2027.
- Who owns South German Gas Pipeline?
- South German Gas Pipeline is owned by Terranets BW, as recorded in the current tracker release.