LNG Chain

Gas transmission pipeline · Vytegra to Krasnoborsky

Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline

Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline is an under construction gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 106 km long and 0.74 bcm/y of capacity, starting up in 2025. It runs from Vytegra to Krasnoborsky. It is owned by Gazprom PJSC.

Length

106 km

Capacity

0.74 bcm/y

0.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 500 mm (20 in)

Route

Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline runs from Vytegra to Krasnoborsky. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Vytegra
To
Krasnoborsky
Start country
Russia
End country
Russia
Countries crossed
Russia
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
96 km
GEM pipeline ID
P4210
Start year
2025
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Stage IV: Vytegra-Pudozh Gas PipelineUnder constructionVytegra → Krasnoborsky1060.74500 mm2025GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline run?
Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline runs from Vytegra to Krasnoborsky, crossing Russia.
How long is Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline?
Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline is 106 km long.
How much gas can Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline carry?
Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline has a design capacity of 0.74 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline operating?
Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline is under construction, with a reported start year of 2025.
Who owns Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline?
Sheksna-Kirillov-Lipin Bor-Vytegra-Pudozh Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.