LNG Chain

Gas transmission pipeline · Sara compressor station to Clarencia measuring center

Sara-Clarencia Gas Pipeline

Sara-Clarencia Gas Pipeline is a proposed gas transmission pipeline in Chile. The tracker lists 1 tracked segment, 60 km long and 0.16 bcm/y of capacity, starting up in 2027. It runs from Sara compressor station to Clarencia measuring center. It is owned by ENAP Magallanes.

Length

60 km

Capacity

0.16 bcm/y

0.1 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 937895 mm (36925 in)

Route

Sara-Clarencia Gas Pipeline runs from Sara compressor station to Clarencia measuring center. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Sara compressor station
To
Clarencia measuring center
Start country
Chile
End country
Chile
Countries crossed
Chile
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
59 km
GEM pipeline ID
P7698
Start year
2027
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineProposedSara compressor station → Clarencia measuring center600.16937895 mm2027GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Sara-Clarencia Gas Pipeline run?
Sara-Clarencia Gas Pipeline runs from Sara compressor station to Clarencia measuring center, crossing Chile.
How long is Sara-Clarencia Gas Pipeline?
Sara-Clarencia Gas Pipeline is 60 km long.
How much gas can Sara-Clarencia Gas Pipeline carry?
Sara-Clarencia Gas Pipeline has a design capacity of 0.16 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Sara-Clarencia Gas Pipeline operating?
Sara-Clarencia Gas Pipeline is proposed, with a reported start year of 2027.
Who owns Sara-Clarencia Gas Pipeline?
Sara-Clarencia Gas Pipeline is owned by ENAP Magallanes, as recorded in the current tracker release.