Gas transmission pipeline · Bangladesh
Mymensingh-Netrokona Gas Pipeline
Mymensingh-Netrokona Gas Pipeline is an operating gas transmission pipeline in Bangladesh. The tracker lists 1 tracked segment, 40 km long and 0.61 bcm/y of capacity, starting up in 1993. It is owned by Titas Gas Transmission and Distribution Co (TGTDCL).
Length
40 km
Capacity
0.61 bcm/y
0.4 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 152 mm (6.0 in)
Route
Mymensingh-Netrokona Gas Pipeline runs from Bangladesh. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Mymensingh
- To
- Not reported
- Start country
- Bangladesh
- End country
- Bangladesh
- Countries crossed
- Bangladesh
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 35 km
- GEM pipeline ID
- P0869
- Start year
- 1993
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Mymensingh → ? | 40 | 0.61 | 152 mm | 1993 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Mymensingh-Netrokona Gas Pipeline run?
- Mymensingh-Netrokona Gas Pipeline is recorded in Bangladesh. Global Energy Monitor reports no start and end points for it.
- How long is Mymensingh-Netrokona Gas Pipeline?
- Mymensingh-Netrokona Gas Pipeline is 40 km long.
- How much gas can Mymensingh-Netrokona Gas Pipeline carry?
- Mymensingh-Netrokona Gas Pipeline has a design capacity of 0.61 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Mymensingh-Netrokona Gas Pipeline operating?
- Mymensingh-Netrokona Gas Pipeline is operating, having started in 1993.
- Who owns Mymensingh-Netrokona Gas Pipeline?
- Mymensingh-Netrokona Gas Pipeline is owned by Titas Gas Transmission and Distribution Co (TGTDCL), as recorded in the current tracker release.