Gas transmission pipeline · Kanbauk to Kyaiklat
Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline
Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline is a shelved gas transmission pipeline in Myanmar. The tracker lists 1 tracked segment, 370 km long, starting up in 2024. It runs from Kanbauk to Kyaiklat. It is owned by PTT Exploration and Production.
Length
370 km
Capacity
Not reported
Segments tracked
1
Route
Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline runs from Kanbauk to Kyaiklat. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Kanbauk
- To
- Kyaiklat
- Start country
- Myanmar
- End country
- Myanmar
- Countries crossed
- Myanmar
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 362 km
- GEM pipeline ID
- P3374
- Start year
- 2024
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Shelved | Kanbauk → Kyaiklat | 370 | Not reported | — | 2024 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Kanbauk FSRU | Myanmar | Import | Cancelled | 24.2 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline run?
- Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline runs from Kanbauk to Kyaiklat, crossing Myanmar.
- How long is Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline?
- Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline is 370 km long.
- How much gas can Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline carry?
- No design capacity is reported for Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline. That is an absent figure, not a zero.
- Is Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline operating?
- Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline is shelved, with a reported start year of 2024.
- Who owns Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline?
- Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline is owned by PTT Exploration and Production, as recorded in the current tracker release.
- Does Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline serve an LNG terminal?
- Kanbauk-Daw Nyein-Kyaiklat Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.