LNG Chain

Gas transmission pipeline · Asaluyeh to Aghajari oil field

IGAT 5 Gas Pipeline

IGAT 5 Gas Pipeline is an operating gas transmission pipeline in Iran. The tracker lists 1 tracked segment, 540 km long and 34.68 bcm/y of capacity, starting up in 2008. It runs from Asaluyeh to Aghajari oil field. It is owned by National Iranian Gas Company.

Length

540 km

Capacity

34.7 bcm/y

25.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

IGAT 5 Gas Pipeline runs from Asaluyeh to Aghajari oil field. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Asaluyeh
To
Aghajari oil field
Start country
Iran
End country
Iran
Countries crossed
Iran
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
496 km
GEM pipeline ID
P8030
Start year
2008
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingAsaluyeh → Aghajari oil field54034.71067 mm2008GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
South Pars LNG TerminalIranExportCancelled0.8 kmroute proximity
Iran NIOC LNG TerminalIranExportUnder construction1.9 kmroute proximity
North Pars LNG TerminalIranExportCancelled2.3 kmroute proximity
Kangan LNG TerminalIranExportShelved4 kmroute proximity
Persian NIOC LNG TerminalIranExportCancelled4 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does IGAT 5 Gas Pipeline run?
IGAT 5 Gas Pipeline runs from Asaluyeh to Aghajari oil field, crossing Iran.
How long is IGAT 5 Gas Pipeline?
IGAT 5 Gas Pipeline is 540 km long.
How much gas can IGAT 5 Gas Pipeline carry?
IGAT 5 Gas Pipeline has a design capacity of 34.7 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is IGAT 5 Gas Pipeline operating?
IGAT 5 Gas Pipeline is operating, having started in 2008.
Who owns IGAT 5 Gas Pipeline?
IGAT 5 Gas Pipeline is owned by National Iranian Gas Company, as recorded in the current tracker release.
Does IGAT 5 Gas Pipeline serve an LNG terminal?
IGAT 5 Gas Pipeline passes within 25 km of 5 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.