LNG Chain

Gas transmission pipeline · Hassi R'Mel to Arzew

Hassi R'Mel-Arzew Gas Pipeline

Hassi R'Mel-Arzew Gas Pipeline is an operating gas transmission pipeline in Algeria. The tracker lists 1 tracked segment, 509 km long and 6.67 bcm/y of capacity, starting up in 1961. It runs from Hassi R'Mel to Arzew. It is owned by Sonatrach SpA.

Length

509 km

Capacity

6.67 bcm/y

4.9 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 51410 mm (2024 in)

Route

Hassi R'Mel-Arzew Gas Pipeline runs from Hassi R'Mel to Arzew. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Hassi R'Mel
To
Arzew
Start country
Algeria
End country
Algeria
Countries crossed
Algeria
Onshore / offshore
Not reported
Fuel
Gas
Region
Africa
Route drawn on map
505 km
GEM pipeline ID
P0466
Start year
1961
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
MainlineOperatingHassi R'Mel → Arzew5096.6751410 mm1961GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Arzew-Bethioua LNG TerminalAlgeriaExportOperating2 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Hassi R'Mel-Arzew Gas Pipeline run?
Hassi R'Mel-Arzew Gas Pipeline runs from Hassi R'Mel to Arzew, crossing Algeria.
How long is Hassi R'Mel-Arzew Gas Pipeline?
Hassi R'Mel-Arzew Gas Pipeline is 509 km long.
How much gas can Hassi R'Mel-Arzew Gas Pipeline carry?
Hassi R'Mel-Arzew Gas Pipeline has a design capacity of 6.67 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Hassi R'Mel-Arzew Gas Pipeline operating?
Hassi R'Mel-Arzew Gas Pipeline is operating, having started in 1961.
Who owns Hassi R'Mel-Arzew Gas Pipeline?
Hassi R'Mel-Arzew Gas Pipeline is owned by Sonatrach SpA, as recorded in the current tracker release.
Does Hassi R'Mel-Arzew Gas Pipeline serve an LNG terminal?
Hassi R'Mel-Arzew Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.