Erawan-Rayon Gas Pipeline 3 is an operating gas transmission pipeline in Thailand. The tracker lists 1 tracked segment, 414 km long and 19.42 bcm/y of capacity, starting up in 2007. It runs from Offshore Thailand to Map Ta Phud. It is owned by PTT Public Co Ltd.

Length

414 km

Capacity

19.4 bcm/y

14.3 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

Erawan-Rayon Gas Pipeline 3 runs from Offshore Thailand to Map Ta Phud. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Offshore Thailand
To
Map Ta Phud
Start country
Thailand
End country
Thailand
Countries crossed
Thailand
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
382 km
GEM pipeline ID
P1109
Start year
2007
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingOffshore Thailand → Map Ta Phud41419.41067 mm2007GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Map Ta Phut LNG Terminal 1ThailandImportOperating0.3 kmroute proximity
Map Ta Phut LNG Terminal 3ThailandImportUnder construction2.6 kmroute proximity
Map Ta Phut LNG Terminal 2ThailandImportOperating5.5 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Erawan-Rayon Gas Pipeline 3 run?
Erawan-Rayon Gas Pipeline 3 runs from Offshore Thailand to Map Ta Phud, crossing Thailand.
How long is Erawan-Rayon Gas Pipeline 3?
Erawan-Rayon Gas Pipeline 3 is 414 km long.
How much gas can Erawan-Rayon Gas Pipeline 3 carry?
Erawan-Rayon Gas Pipeline 3 has a design capacity of 19.4 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Erawan-Rayon Gas Pipeline 3 operating?
Erawan-Rayon Gas Pipeline 3 is operating, having started in 2007.
Who owns Erawan-Rayon Gas Pipeline 3?
Erawan-Rayon Gas Pipeline 3 is owned by PTT Public Co Ltd, as recorded in the current tracker release.
Does Erawan-Rayon Gas Pipeline 3 serve an LNG terminal?
Erawan-Rayon Gas Pipeline 3 passes within 25 km of 3 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.