LNG Chain

Gas transmission pipeline · Stavropolsky District to Ulyanovsk

Binaradka-Ulyanovsk Gas Pipeline

Binaradka-Ulyanovsk Gas Pipeline is an operating gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 214 km long and 4.2 bcm/y of capacity, starting up in 1969. It runs from Stavropolsky District to Ulyanovsk. It is owned by Gazprom PJSC.

Length

214 km

Capacity

4.2 bcm/y

3.1 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 530 mm (21 in)

Route

Binaradka-Ulyanovsk Gas Pipeline runs from Stavropolsky District to Ulyanovsk. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Stavropolsky District
To
Ulyanovsk
Start country
Russia
End country
Russia
Countries crossed
Russia
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
144 km
GEM pipeline ID
P2286
Start year
1969
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingStavropolsky District → Ulyanovsk2144.2530 mm1969GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Binaradka-Ulyanovsk Gas Pipeline run?
Binaradka-Ulyanovsk Gas Pipeline runs from Stavropolsky District to Ulyanovsk, crossing Russia.
How long is Binaradka-Ulyanovsk Gas Pipeline?
Binaradka-Ulyanovsk Gas Pipeline is 214 km long.
How much gas can Binaradka-Ulyanovsk Gas Pipeline carry?
Binaradka-Ulyanovsk Gas Pipeline has a design capacity of 4.2 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Binaradka-Ulyanovsk Gas Pipeline operating?
Binaradka-Ulyanovsk Gas Pipeline is operating, having started in 1969.
Who owns Binaradka-Ulyanovsk Gas Pipeline?
Binaradka-Ulyanovsk Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.