Gas transmission pipeline · Baumgarten to Breclav
Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI)
Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) is a shelved gas transmission pipeline crossing Austria, Czechia. The tracker lists 1 tracked segment, 62 km long and 6.5 bcm/y of capacity, starting up in 2026. It runs from Baumgarten to Breclav. It is owned by Gas Connect Austria GmbH and Net4Gas.
Length
62 km
Capacity
6.5 bcm/y
4.8 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 800 mm (32 in)
Route
Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) runs from Baumgarten to Breclav. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Baumgarten
- To
- Breclav
- Start country
- Austria
- End country
- Czech Republic
- Countries crossed
- Austria, Czechia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 116 km
- GEM pipeline ID
- P1693
- Start year
- 2026
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Shelved | Baumgarten → Breclav | 62 | 6.5 | 800 mm | 2026 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) run?
- Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) runs from Baumgarten to Breclav, crossing Austria and Czechia.
- How long is Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI)?
- Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) is 62 km long.
- How much gas can Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) carry?
- Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) has a design capacity of 6.5 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) operating?
- Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) is shelved, with a reported start year of 2026.
- Who owns Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI)?
- Bidirectional Austrian-Czech Interconnector Gas Pipeline (BACI) is owned by Gas Connect Austria GmbH and Net4Gas, as recorded in the current tracker release.