Beanibazar-Kailashtila Gas Pipeline is an operating gas transmission pipeline in Bangladesh. The tracker lists 1 tracked segment, 18 km long and 2.04 bcm/y of capacity, starting up in 2001. It runs from Beanibazar to Kailashtila Gas Field. It is owned by Gas Transmission Co Ltd (GTCL).

Length

18 km

Capacity

2.04 bcm/y

1.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 508 mm (20 in)

Route

Beanibazar-Kailashtila Gas Pipeline runs from Beanibazar to Kailashtila Gas Field. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Beanibazar
To
Kailashtila Gas Field
Start country
Bangladesh
End country
Bangladesh
Countries crossed
Bangladesh
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
14 km
GEM pipeline ID
P0842
Start year
2001
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingBeanibazar → Kailashtila Gas Field182.04508 mm2001GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Beanibazar-Kailashtila Gas Pipeline run?
Beanibazar-Kailashtila Gas Pipeline runs from Beanibazar to Kailashtila Gas Field, crossing Bangladesh.
How long is Beanibazar-Kailashtila Gas Pipeline?
Beanibazar-Kailashtila Gas Pipeline is 18 km long.
How much gas can Beanibazar-Kailashtila Gas Pipeline carry?
Beanibazar-Kailashtila Gas Pipeline has a design capacity of 2.04 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Beanibazar-Kailashtila Gas Pipeline operating?
Beanibazar-Kailashtila Gas Pipeline is operating, having started in 2001.
Who owns Beanibazar-Kailashtila Gas Pipeline?
Beanibazar-Kailashtila Gas Pipeline is owned by Gas Transmission Co Ltd (GTCL), as recorded in the current tracker release.